Search
  • A+
  • A-

Current & Future Projects

Village of Bellevue » Departments » Public Works » Projects & Construction » Current & Future Projects

Project Description 
2017 + State/County
Construction
  • The Wisconsin DOT will be doing some safety improvements to STH 172 from Webster Ave. to I-43. These improvements will include regrading of existing median and installation of new cable guard on this section of roadway. In order to reduce the amount of delays to traveling public, this work will take place during nighttime hours 7 pm to 6 am, Sunday thru Thursday starting July 17. There will be some noise and lighting from construction vehicles working in the median, most of the noise will be from the grading operations. This work will proceed from one end of project to the other, so if you hear construction vehicles one night, they may be moved further away by the following night. It will take about a month to complete grading, and then some extra time to place cable guard.            

For the latest updates on State-DOT projects in northeast Wisconsin visit the 511 Construction Projects page.

2017 Village Crack Filling Program - COMPLETED 2017 program contractor has been approved. Work has been completed for 2017. The provided Crack Fill Program map details roads that were scheduled for work.
2017 Culvert Replacement Program The Village has contracted to have several culverts removed and replaced in 2017. During completion, the project area affected may require a road closure. Work is scheduled to start the week of August 14.  2017 Culvert Projects
Village Street Resurfacing

This map is the Village's current street construction program for 2017-2021. The Village Board will be reviewing the proposed 2018-2022 program in early August, 2017.

A list of Frequently Asked Questions is also available for viewing regarding Village construction and assessments.

Townhall Road Construction

Construction is currently in progress. The project involves sanitary sewer main and lateral replacement, new sidewalk and trees, as well as curb repair and pavement replacement. Sidewalks are being installed on the south side of the road from Lime Kiln Rd. to Nicole Ann Circle (west).

An informational meeting was held on 8/23/2016. Bids were opened for the projects on October 26 and rejected. Staff and the Village Board re-evaluated construction methods and then re-bid the project. Construction bids were then approved on 3/22/2017.

Handouts, mailings and presentations available are posted below:

 - Village Board presentation 3/8/2017
 - Notice of Public Hearing & Report on Proposed Special Assessments
 - Village Board presentation 3/22/2017 
 Final Resolution

Construction Updates

  - 4-17-2017 Construction Update
  - 6-9-2017 Construction Update
  - 6-22-2017 Construction Update
  - 7-31-2017 Construction Update

2017 Resurfacing Program (Denmark State Bank Subdivision Area)

Streets included in the program are Valley Heights, Foxfire, Woodgate, Woodland Hills, Bel Meadow, Vonda, and Meadow Park. Select curb replacement will be performed, as well as gravel base reconditioning and new pavement. This project has been completed.

Handouts, mailings and presentations are posted below:

 - Village Board presentation 3/8/17 (see above for PDF link)
 - Village Board presentation 3/22/17 (see above for PDF link)
 - Notice of Public Hearing & Report on Proposed Special Assessments
  - Final Resolution    

Construction Updates

  - 4-17-2017 Construction Update
  - 5-19-2017 Construction Update
  - Construction Start Notice
  - 6-9-2017 Construction Update

2017 Sidewalk Improvements Sidewalk Map

Construction dates on the map are subject to change.

2017 sidewalk projects are on-going for Town Hall Road. A small segment on Allouez Ave. and within DeBroux Park has been completed. The Huron Road Trail from Eaton Rd. to the north is currently under construction for re-paving and is scheduled to be completed soon.
 County Trunk Highway (CTH) EA/South Huron Road Brown County in cooperation with the Village will be making improvements to CTH EA/South Huron Road (Willow Rd.-STH 29). The roadway will be fully urbanized and include intersection traffic control improvements. Construction is scheduled to be completed in 2019. Public meetings on the project may begin as soon as November, 2017.
 Manitowoc Road Project The Village will be making improvements to Manitowoc Road from Allouez Ave to Kewaunee Rd. Design and engineering for the project is on-going in 2017-2018. Construction is scheduled to be completed in 2021.

Proposed work is planned to include road resurfacing, sidewalk installation, and a traffic control improvement (TBD) at the Manitowoc/Ontario intersection.

Upcoming Events

No events available.