Project Schedule:
- PIM #2 – September 11, 2012
- Decision from Local Officials - October 2012
- Local Cost Share Agreement - January 2013
- Environmental Report Complete - March 2013
- Complete Study - April 2013
- Construction is dependent on future project funding availability